First Floor Extension

First Floor - Extension Work

First Floor – Extension Work

BUDGET FOR CONSTRUCTING THE REMAINING WORKS OF 45 BED FIRST FLOOR (PART OF 100 BED HOME)

A Tentative (valid until 2011) Estimation of Building Expenses

The Construction of First floor costs lesser than the ground floor due to no need of foundation:

A Tentative Estimation of Building Expenses
Construction cost per Square feet = Rs. 2,600.00
(The cost is valid till December 2013)
INR USD GBP
Third Dormitory (for 15 residents) 1350 Sq. feet 3,510,000 57,038 34,701
Fourth Dormitory (for 15 residents) 1080 Sq. feet 2,808,000 45,630 27,762
Fifth Dormitory (for 15 residents) 1350 Sq. feet 3,510,000 57,038 34,701
Toilet 800 Sq. feet 2,080,000  45,630  27,762
Office Room 540 Sq. feet 1,404,000 22,815 13,881
Staff Room 540 Sq. feet 1,404,000 22,815 13,881
Washing Room 270 Sq. feet 702,000  11,408 6,940
Ramp 375,000 6,094 3,707
Total 5930 Sq. feet 15,793,000 256,636  156,139